What could you do with better internet?

Check your Eligibility:

Find out if service is available at your location by inputting your address and pressing "Go":

Updates

2022 December Construction Update

2:39PM January 03, 2023

***DATES BELOW EACH ZONE ARE ESTIMATED MAINLINE CONSTRUCTION DATES***

See "Important Definitions" below for more details.

Phase 4:

• Camino zone's final cabinets were tested and completed the week of December 14. Installations are ongoing in this area.

Phase 5:

• Knott zone's construction is complete. Splicing in this area is ongoing with hopes of connecting homes by the end of January.

• Sassafras zone's construction is complete with splicing to begin the week of December 12. Hoping to begin connecting homes shortly after the new year.

• Oxbow zone's construction is being spliced with hopes to connect homes by the end of January.

• Diamond zone's construction is expected to be completed and spliced by the end of January with homes to begin being installed shortly after.

• Pearl zone's construction is ongoing with two different crews working there. 

• Vandecar zone's construction began in mid-December with construction expected to wrap up in February.

• Littlefield's construction is slated to begin in early January.

• Evergreen zone is having underground contractors move into the area to stay ahead of the aerial crews. 

Overall Notes:

• We have begun laying temp drops as the ground has frozen in most areas. 


View more updates